4.8

Google Reviews

Need Help? Contact An Australian Business Lawyer Today 1300 003 077

When are Liquidated Damages Unenforceable? 

In commercial contracts, liquidated damages clauses provide clarity and certainty when a party breaches the agreement. They pre-define financial consequences (often for delays or non-performance) helping parties avoid disputes over actual loss. But if these clauses impose excessive or punitive amounts, they may be ruled unenforceable by Australian courts.

This article, written by our building and construction law team, explains what liquidated damages are, when they cross the line into unenforceable penalties, and how to draft clauses that courts are likely to uphold.

Key Takeaways

  • Liquidated damages must reflect a genuine pre-estimate of loss

  • Penalty clauses are unenforceable under Australian contract law

  • Courts assess reasonableness at the time of contracting

  • Clauses must be proportionate and commercially justified

  • Good drafting = better enforceability and lower risk

Allison Inskip is a Senior Paralegal and highly experienced legal professional

What Are Liquidated Damages?

Liquidated damages are pre-agreed sums payable for specific breaches of contract, commonly used in construction contracts, consultancy agreements, and leases.

Their primary benefit is avoiding the need to prove actual loss, which can be costly and uncertain.

For a more detailed explanation of what liquidated damages are and how they work, see our separate guide.

When Are Liquidated Damages Clauses Unenforceable?

A clause will be unenforceable if it amounts to a penalty, rather than a genuine attempt to compensate for loss in the event of a contract breach by a party.  

A clause may be found to be a penalty and therefore unenforceable if it: 

  • Imposes an amount that is extravagant or out of proportion to the likely loss 
  • Lacks a reasonable basis or commercial justification 
  • Appears designed to deter breach rather than compensate for it 
  • Applies the same amount to all breaches, regardless of the actual impact 

Courts focus on whether the amount was a reasonable attempt to estimate likely loss at the time of contracting, not whether it matched actual loss.

Learn more about penalties vs liquidated damages in our article.

Case Law – What Do the Courts Say?

In Bellas v Powers [2023], the court ruled a clause unenforceable where a lender sought over $7.8 million on a $3 million loan default. The default interest rate was more than five times the standard rate. The court found no evidence it reflected the lender’s real losses and ruled the clause a penalty clause.

Contrast that with Growthbuilt Pty Ltd v Modern Touch Marble & Granite Pty Ltd [2021], where a $3,500/day delay clause in a subcontract was upheld. The court found the rate reasonable given the project scale and potential commercial losses.

Key takeaways: Proportionality, commercial logic, and documentation at the time of contract formation are essential for enforceability.

Prosper Law legal team

Tips for Drafting Enforceable Clauses

In summary, a liquidated damage clause should align with the agreement’s commercial reality and be backed by a legitimate interest. To ensure that liquidated damages in clauses are enforceable, the below is recommended:

Tip 

Description 

Use Real Data and Commercial Forecasts 

Base liquidated damages on tangible data like project timelines, financing costs, or delay penalties. This supports the amount as a genuine pre-estimate of loss. 

Avoid Rounded Figures 

Avoid arbitrary figures like “$5,000 per day.” Use specific calculations (e.g., overhead per day) to justify the amount. 

Document Rationale During Negotiations 

Keep records of how the amount was determined (e.g., internal assessments, correspondence). This helps prove the clause is fair and reasonable. 

Tailor the Clause to the Breach 

Match the damages amount to the type and severity of the breach. Use different rates for different breach types where appropriate. 

Ensure the Clause is Not One-Sided or Punitive 

Avoid clauses that unfairly punish one party. The amount should reflect actual risk and loss, not act as a deterrent. 

Frequently Asked Questions

What is the difference between liquidated damages and penalties?

Liquidated damages are compensatory, pre-agreed amounts for specific breaches. Penalties are designed to punish and are generally unenforceable. 

Can liquidated damages be enforced without actual loss?

Yes. If the clause reflects a reasonable pre-estimate of loss at the time of contracting, courts may enforce it even if actual loss is minimal or nil. 

How can I prove that a clause is enforceable?

Keep records of how the amount was calculated, including cost projections, historical data, and contract negotiations. 

Are liquidated damages clauses allowed in consumer contracts?

Yes, but they must comply with Australian Consumer Law. If a clause is unfair, causes a significant imbalance between the parties, or is not necessary to protect a legitimate interest, it may be void. 

What happens if a clause is unenforceable?

The clause will be struck out, and the non-breaching party must rely on general damages, often more costly and difficult to prove. 

About the Author

Farrah Motley
Director of Prosper Law. Farrah founded Prosper online law firm in 2021. She wanted to create a better way of doing legal work and a better experience for customers of legal services.

Contact an Australian Business Lawyer Today.

Contact us for a free consultation

Contact Us For A Free Legal Consultation
About Prosper Law

We provide legal advice to business and individuals across Australia, no matter which State or Territory you are located. Our easy-to-access, online legal services mean that you can talk to our lawyers wherever you are, at a time that suits you.

4.8

Google Reviews

Get Your Free Guide Now
Need Legal Assistance?

Don’t hesitate – reach out for your free legal assistance today. Your peace of mind is just a click or call away!

Check Out Our Latest Blog Posts

Stephen Motley is the Legal Operations Manager of Prosper Law
Building and Construction

Mandatory Professional Indemnity Insurance in NSW 

From 1 July 2025, all registered building and design practitioners in NSW must hold mandatory professional indemnity (PI) insurance under the Design and Building Practitioners Act 2020 (NSW). This update,

Sharna Arnold is a Senior Paralegal at Prosper Law
Building and Construction

Who Owns the Plans in a Building Project?  

Plans, drawings, specifications and digital models are vital to any construction project. Whether you’re a builder, engineer, carpenter, designer or project owner – understanding who owns these materials is critical.

Farrah Motley is an Australian Legal Practitioner and the Director of Prosper Law
Building and Construction

What is Practical Completion in Construction?

Practical completion is a critical milestone in Australian construction projects. It marks the end of most contractor obligations, triggers the release of retention money, stops liquidated damages, and starts the